Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.82 | 0.82 | 0.82 | 0 |
56W193 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 5109(1)/111(2)/11 एम0एल0ए0/2011, दिनांक 15-11-2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
105.50
Resanction Cost :
105.50
Tentative Cost :
105.50
Exp. Upto Last Fy : 17.02
For CFY 2024-2025
Remaining : 88.48
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 17.02
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
12 years 8 months ago
15 Nov 2011
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
गैर वनभूमि भाग में 200 मी0 तक कार्य पूर्ण शेष वनभूमि भाग का वनभूमि प्रस्ताव संख्या एफ0पी0/यू0के0/रोड़ 146873/2021 के द्वारा आपलोड किया गया था जिस पर वन विभा द्वारा आपत्ति लगाई गई थी जिसका आपत्ति का निस्तारण कर दिनांक 10.05.2022 को अपलोड कर दिया गया है। डी0एफ0ओ0 स्तर से संबन्धित आपत्ति का निराकरण किया जाना हैं। प्रमुख अपर वन संरक्षक के पत्रांक संख्या 2107/एफ0पी0/यू0के0/रोड/146873/2021 दिनांक 06.03.2023 द्वारा आपत्ति गाई गई थी। जिसका निराकरण किया जा रहा हैं। -- as on 19-Apr-2023
Physical Peramenters