Administrative Approval Detail : शासन के ई-पत्रावली संख्या 45425 दिनांक 13.02.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7.50
Resanction Cost :
7.50
Tentative Cost :
7.50
Exp. Upto Last Fy :
0.44
For CFY 2025-2026
Remaining :
7.06
Demand :
1.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.44
Alignment Approved
Sanction on : 2 years 10 months ago
13 Feb 2023
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
6 %
Tentative Completion date on : 6 months 2 weeks from now
30 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ग्रामीणें की सहमति प्राप्त हो गई है। विस्तृत डिज़ाईन की कार्यवाही गतिमान है। -- as on 09-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: