Work Profile Report [56W698]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : उत्तराखण्ड़ शासन के पत्रांक संख्या 272/।।।(2)/2024-01(प्रा0आ0)/2023 लोक निर्माण अनुभाग-2 देहरादून दिनांक 31 जनवरी, 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
193.50
Resanction Cost :
193.50
Tentative Cost :
190.49
Saving
3.01
Exp. Upto Last Fy :
173.97
For CFY 2025-2026
Remaining :
19.53
Demand :
19.53
Allotment :
19.53
Exp in CFY :
16.53
Total Up to Date Exp :
190.49
Work completed
Sanction on : 1 year 10 months ago
31 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 2 weeks ago
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 3.01 has been recorded as expected cost of work reduced from 193.5 to 190.49 . -- as on 09-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: