Work Profile Report [56W699]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासन के ई-प्रत्रावली सख्या 63074 लोक निर्माण अनुभाग-2 देहरादून दिनांक 14 मार्च 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
358.53
Resanction Cost :
358.53
Tentative Cost :
358.53
Exp. Upto Last Fy :
11.59
For CFY 2024-2025
Remaining :
346.94
Demand :
134.95
Allotment :
87.76
Exp in CFY :
70.76
Total Up to Date Exp :
82.35
Construction Started
Sanction on : 9 months 1 week ago
14 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
15 %
Tentative Completion date on : 1 year 5 days from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर हैं। -- as on 07-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: