Work Profile Report [56W701]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : न्याय विभाग के पत्र संख्या 4376/IX/1-7/budget(UHC)/23-24 दिनांक 09.08.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
26.29
Resanction Cost :
26.29
Tentative Cost :
26.29
Exp. Upto Last Fy :
3.65
For CFY 2024-2025
Remaining :
22.64
Demand :
22.64
Allotment :
22.64
Exp in CFY :
13.48
Total Up to Date Exp :
17.14
Construction Started
Sanction on : 1 year 3 months ago
09 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
50 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर हैं। -- as on 06-May-2024