Length of Road [Km] | 7 | 7 | 7 | 0 |
56W71 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1398/111/-(2)/05-48(प्रा0आ0)/05 दि0 29/08/05
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
97.00
Resanction Cost :
97.00
Tentative Cost :
97.00
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 97.00
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
18 years 10 months ago
29 Aug 2005
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
अधीक्षण अभियन्ता के पत्रांक सं0 387/342(25)सी0-9/21 दिनांक 27.1.2021 के द्वारा संमरेखण स्वीकृत। वनभूमि प्रस्ताव दिनांक 22-03-2023 को आनलाईन अपलोड कर दिया गया है। दिनांक 06-09-2023 को आनलाईन आपत्ति लगायी गयी जिसका निराकरण कर इस कार्यालय के पत्रांक सं0 1887/6सी0 दिनांक 17-10-2023 के द्वारा प्रभागीय वनाधिकारी चकराता को प्रेषित। (वन प्रभाग स्तर पर है।) -- as on 03-Jan-2024