Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.85 | 4.85 | 4.85 | 0 |
59W1935 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4014/।।।(2)/21-29(एम.एल.ए.) /2017टी0सी0-।। देहरादून दि0 17.09.2021
TS Amount (lakhs) : 247.83 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
247.83
Resanction Cost :
247.83
Tentative Cost :
247.83
Exp. Upto Last Fy : 259.79
For CFY 2024-2025
Remaining : -11.96
Demand : 14.00
Allotment : 14.46
Exp in CFY : 14.46
Total Up to Date Exp : 274.25
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
17 Sep 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्वों के भुगतान शेष। -- as on 18-Apr-2023
Physical Peramenters