Work Profile Report [59W2202]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-58709 दिनांक 11.10.2023
TS Amount (lakhs) : 41.54 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
41.54
Resanction Cost :
41.54
Tentative Cost :
41.54
Exp. Upto Last Fy :
31.02
For CFY 2024-2025
Remaining :
10.52
Demand :
10.00
Allotment :
8.55
Exp in CFY :
8.55
Total Up to Date Exp :
39.57
Work completed
Sanction on : 1 year 2 months ago
11 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
79 %
Up to Date :
100 %
Tentative Completion date on : 6 months 3 weeks ago
31 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 05/2024 -- as on 04-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: