Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.05 | 1.05 | 0.600 | 0.45 | 0.450 | 0.300 |
59W2212 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55552 दिनांक 30.10.2023
TS Amount (lakhs) : 27.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
27.50
Resanction Cost :
27.50
Tentative Cost :
27.50
Exp. Upto Last Fy : 10.75
For CFY 2024-2025
Remaining : 16.75
Demand : 10.00
Allotment : 0.28
Exp in CFY : 0.53
Total Up to Date Exp : 11.27
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 86 %
Sanction on :
8 months 2 weeks ago
30 Oct 2023
Tentative Completion date:
17 hours 41 seconds from now
18 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
900 मी0 खडण्जा कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 27-Jun-2024
Physical Peramenters