Work Profile Report [59W2220]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55552 दिनांक 29.11.2023
TS Amount (lakhs) : 47.66 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.66
Resanction Cost :
47.66
Tentative Cost :
47.66
Exp. Upto Last Fy :
9.59
For CFY 2024-2025
Remaining :
38.07
Demand :
38.00
Allotment :
1.36
Exp in CFY :
29.24
Total Up to Date Exp :
38.82
Construction Started
Sanction on : 11 months 3 weeks ago
29 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
50 %
Tentative Completion date on : 1 month 1 week from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में। -- as on 06-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: