Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.495 | 1.495 | 0.500 | 0.995 | 1.000 | 1.000 |
59W2230 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई0 फाईल संख्या- 50282 दिनांक 24.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
95.21
Resanction Cost :
95.21
Tentative Cost :
95.21
Exp. Upto Last Fy : 32.74
For CFY 2024-2025
Remaining : 62.47
Demand : 38.00
Allotment : 32.86
Exp in CFY : 34.96
Total Up to Date Exp : 67.69
Work completed
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 100 %
Sanction on :
5 months 3 weeks ago
24 Jan 2024
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 05/2024 -- as on 04-Jun-2024
Physical Peramenters