Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.58 | 0.58 | 0.200 | 0.38 | 0.380 | 0.380 |
59W2234 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-53351/29 दिनांक 31.01.2024
TS Amount (lakhs) : 18.45 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.45
Resanction Cost :
18.45
Tentative Cost :
18.45
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 18.45
Demand : 13.00
Allotment : 0.00
Exp in CFY : 8.91
Total Up to Date Exp : 8.91
Work completed
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 100 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
3 weeks 6 hours ago
26 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 06/2024 -- as on 27-Jun-2024
Physical Peramenters