Work Profile Report [59W2247]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-46667/31 दिनांक 07.03.2024
TS Amount (lakhs) : 91.55 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
91.55
Resanction Cost :
91.55
Tentative Cost :
91.55
Exp. Upto Last Fy :
0.14
For CFY 2024-2025
Remaining :
91.41
Demand :
65.00
Allotment :
56.23
Exp in CFY :
56.23
Total Up to Date Exp :
56.37
Work completed
Sanction on : 9 months 2 weeks ago
07 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 12/2024 -- as on 20-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: