Work Profile Report [59W2326]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55435/30 दि0 11.02.2025
TS Amount (lakhs) : 62.55 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
62.55
Resanction Cost :
62.55
Tentative Cost :
62.55
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
62.55
Demand :
62.50
Allotment :
24.87
Exp in CFY :
24.87
Total Up to Date Exp :
24.87
Construction Started
Sanction on : 6 months 2 weeks ago
11 Feb 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
83 %
Tentative Completion date on : 1 month 2 weeks from now
15 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
800 मी0 में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 28-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: