Work Profile Report [59W2374]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-46667/31 दि0 26.08.2025
TS Amount (lakhs) : 93.12 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
93.12
Resanction Cost :
93.12
Tentative Cost :
93.12
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
93.12
Demand :
85.00
Allotment :
23.88
Exp in CFY :
23.88
Total Up to Date Exp :
23.88
Construction Started
Sanction on : 4 months 4 weeks ago
26 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
80 %
Tentative Completion date on : 3 months 3 weeks from now
17 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
80 प्रतिशत कार्यपूर्ण, शेष कार्य प्रगति पर है। -- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: