Work Profile Report [5W218]

बागेश्वर-देवलधार-मैथाण-लेटी-गिरेछीना मोटर मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शा0सं0 824/111-2/08-43(एम0एल0ए0)/07 दिनांक 24.03.2008 रू0 61.00 लाख

TS Amount (lakhs) : 441 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

441.00

Resanction Cost :

441.00

Tentative Cost :

441.00

Exp. Upto Last Fy :

294.63

For CFY 2024-2025

Remaining :

146.37

Demand :

75.99

Allotment :

51.00

Exp in CFY :

1.88

Total Up to Date Exp :

296.51

Construction Started

Sanction on : 16 years 4 months ago

24 Mar 2008

Physical Progress:

At start of FY 2024-2025 :

75 %

Up to Date :

80 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
12
6
5.500
0.5
0.500
0.000

Remark

view all

6.00 किमी0 पहाड़ कटान एवं 6.00 किमी0 पार्ट-।। कार्य पूर्ण। -- as on 13-Jul-2024

Rating : 80

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck