Work Profile Report [5W234]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 1440/।।।(2)/11-05(प्रा0आ0)/ 2010, दिनांक 28.03.2011
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.40
Resanction Cost :
50.40
Tentative Cost :
50.40
Exp. Upto Last Fy :
38.39
For CFY 2025-2026
Remaining :
12.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
38.39
Alignment Approved
Sanction on : 14 years 1 month ago
28 Mar 2011
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मुआवजा fवतरण fकया जाना है। द्वितीय चरण में मोटर मार्ग का निर्माण कार्य पूर्ण। -- as on 27-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand