Work Profile Report [5W25]

जनपद बागेश्वर में बागेश्वर-दफोट मोटर मार्ग का बनकोट तक विस्तार (किमी0 16 से 33 तक) एक सेतु सहित।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 196 /लो0नि0-2 /04-10 (प्रा0आ0)/ 2004 दिनांक 17-2-2004

TS Amount (lakhs) : 677.88 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

381.18

Resanction Cost :

530.57

Tentative Cost :

530.57

Exp. Upto Last Fy :

371.59

For CFY 2025-2026

Remaining :

158.98

Demand :

0.50

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

371.59

Work completed

Sanction on : 21 years 5 months ago

17 Feb 2004

Physical Progress:

At start of FY 2025-2026 :

75 %

Up to Date :

75 %

Tentative Completion date on : 1 year 11 months ago

30 Aug 2023

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
25
18
18.000
0
0.000
0.000
Bridge
1
0
0 (0.000m)
0
0 (0.000m)
0 (0.000m)

Remark

view all

पहाड़ कटान एवं पार्ट-।। का कार्य पूर्ण। सेतु का कार्य वल्र्ड बैंक खण्ड द्वारा पूर्ण। किमी0 27 से 30 में ठेकेदार के अनुबन्ध का अन्तिमीकरण अर्थदण्ड लगाकर कर दिया गया। परन्तु ठेकेदार द्वारा न्यायालय/आर्बिटेशन में वाद दायर की गयी है। दिनांक 04.08.2025 को आर्बिटेशन में तिथि निर्धारित थी एवं अग्रिम तिथि दिनांक 22.08.2025 को नियत की गयी है। -- as on 05-Aug-2025

Rating : 75

No Forest Case in The Work

Hindrance / Bottleneck : Court Case

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand