Work Profile Report [5W280]

जनपद बागेश्वर में बागेश्वर काण्डा मोटर मार्ग के कम्पास तोक मनकोट से तल्लामनकोट तक लिंक मोटर मार्ग (प्रथम चरण)।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 5423/।।।(2)/10-18(प्रा0आ0)/2010, दिनांक 27.08.2010

TS Amount (lakhs) : 25.2 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

25.20

Resanction Cost :

25.20

Tentative Cost :

25.20

Exp. Upto Last Fy :

0.38

For CFY 2025-2026

Remaining :

24.82

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.38

Alignment Approved

Sanction on : 14 years 11 months ago

27 Aug 2010

Physical Progress:

At start of FY 2025-2026 :

50 %

Up to Date :

50 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
2
2
2
-

Remark

view all

विधिवत स्वीकृति प्राप्त। -- as on 24-Dec-2023

Rating : 50

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: