Work Profile Report [5W31]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2503/111-(2)/06-37 (प्रा0आ0)/06दिनांक 20.09.2006 एवं 1205/।।।(2)/16-37(प्रा0आ0)/06 टी0सी0-1, दिनांक 29.02.2016
TS Amount (lakhs) : 305.26 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
305.26
Resanction Cost :
305.26
Tentative Cost :
305.26
Exp. Upto Last Fy :
199.26
For CFY 2024-2025
Remaining :
106.00
Demand :
8.60
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
199.26
Work completed
Sanction on : 18 years 2 months ago
20 Sep 2006
Physical Progress:
At start of FY 2024-2025 :
85 %
Up to Date :
85 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 29-Aug-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: