Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 |
5W32 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2503/111-(2)/06-37 (प्रा0आ0)/06दिनांक 20.09.2006
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
88.60
Resanction Cost :
88.60
Tentative Cost :
88.60
Exp. Upto Last Fy : 0.16
For CFY 2024-2025
Remaining : 88.44
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.16
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
17 years 9 months ago
20 Sep 2006
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 11: AIP Division
Bottelneck: no issue
भारत सरकार के पत्रांक 8बी0/यू0सी0पी0/06/50/2023/एफ0सी0, दिनांक 19.02.2024 द्वारा सैद्धान्तिक स्वीकृति प्राप्त। माह जून 2024 में एन0पी0वी0 का भुगतान कर दिया गया है। -- as on 13-Jul-2024
Physical Peramenters