Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
5W466 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 6108/।।।(2)/14-33(प्रा0आ0)/2014, दिनांक 19.12.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
51.03
Resanction Cost :
51.03
Tentative Cost :
51.03
Exp. Upto Last Fy : 0.48
For CFY 2024-2025
Remaining : 50.55
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.48
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
9 years 6 months ago
19 Dec 2014
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
पुनरीक्षित समरेखण सवीकृत। वनभूमि प्रस्ताव गठन की कार्यवाही की जा रही है। -- as on 21-Dec-2022
Physical Peramenters