Work Profile Report [5W49]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 288 /लो00ि-2 /2004-15 (प्रा0आ0)/ 2004 लो0नि00 अनु0-2 दिनांक 27-2-2004
TS Amount (lakhs) : 208.5 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
208.50
Resanction Cost :
208.50
Tentative Cost :
175.39
Saving
33.11
Exp. Upto Last Fy :
170.49
For CFY 2025-2026
Remaining :
38.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
170.49
Work completed
Sanction on : 21 years 10 months ago
27 Feb 2004
Physical Progress:
At start of FY 2025-2026 :
76 %
Up to Date :
76 %
Tentative Completion date on : 5 years 9 months ago
31 Mar 2020
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पुनरीक्षित आगणन ई.डी.पी.आर. के माध्यम से गठित किया जा रहा है। -- as on 01-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: