Administrative Approval Detail : शा0सं0 1730/।।।(2)/14-03(मु.मं.घो.)/2014 दिनांक 24.08.2014
TS Amount (lakhs) : 43.25 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
43.25
Resanction Cost :
43.25
Tentative Cost :
43.25
Exp. Upto Last Fy :
41.11
For CFY 2025-2026
Remaining :
2.14
Demand :
0.00
Allotment :
1.66
Exp in CFY :
1.66
Total Up to Date Exp :
42.76
Alignment Approved
Sanction on : 10 years 8 months ago
24 Aug 2014
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सैद्धान्तिक स्वीकृति प्राप्त। मुआवजा वितरण किया जाना है। द्वितीय चरण (स्टेज-।) का कार्य पूर्ण। -- as on 27-Oct-2024