Work Profile Report [5W70]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2490/111-2 /08-61 (प्रा0आ0)/ 2007 दि0 25.07.2008
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
220.50
Resanction Cost :
220.50
Tentative Cost :
0.53
Saving
219.97
Exp. Upto Last Fy :
0.43
For CFY 2025-2026
Remaining :
220.07
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.43
Alignment Approved
Sanction on : 17 years 5 months ago
25 Jul 2008
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 3 years 2 months from now
31 Mar 2029
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वनभूमि प्रस्ताव आनलाईन। वर्तमान में आपत्तियों में प्राप्त। -- as on 01-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: