Work Profile Report [5W751]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 700/।।।(2)/19-47(एम0एल0ए0)/2017, दिनांक 18.02.2019
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
15.10
Resanction Cost :
15.10
Tentative Cost :
15.10
Exp. Upto Last Fy :
7.98
For CFY 2024-2025
Remaining :
7.12
Demand :
6.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
7.98
Survey work done
Sanction on : 5 years 10 months ago
18 Feb 2019
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
20 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वेक्षण स्तर पर। समरेखन प्रस्ताव प्रेषित। -- as on 30-Sep-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand