Work Profile Report [5W759]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 710/।।।(2)/19-47(एम0एल0ए0)/2017 टी.सी.-।, दिनांक 18.02.2019
TS Amount (lakhs) : 27.6 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
27.60
Resanction Cost :
27.60
Tentative Cost :
27.60
Exp. Upto Last Fy :
1.06
For CFY 2025-2026
Remaining :
26.54
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.06
Alignment Approved
Sanction on : 6 years 2 months ago
18 Feb 2019
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वनभूमि प्रस्ताव दिनांक 05.10.2023 को आनलाईन कर दिया गया है। -- as on 06-Oct-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand