Work Profile Report [5W860]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 6436(1)/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0, दिनांक 23.12.2021
TS Amount (lakhs) : 212.56 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
212.56
Resanction Cost :
212.56
Tentative Cost :
212.56
Exp. Upto Last Fy :
135.73
For CFY 2024-2025
Remaining :
76.83
Demand :
48.03
Allotment :
45.00
Exp in CFY :
48.35
Total Up to Date Exp :
184.08
Work completed
Sanction on : 2 years 11 months ago
23 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
65 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 13-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: