Work Profile Report [5W890]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/91391/2023 ई-फाइल संख्या-31978, दिनांक 16.01.2023
TS Amount (lakhs) : 14.9 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
14.90
Resanction Cost :
14.90
Tentative Cost :
14.90
Exp. Upto Last Fy :
3.11
For CFY 2025-2026
Remaining :
11.79
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3.11
Alignment Approved
Sanction on : 2 years 3 months ago
16 Jan 2023
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अधीक्षण अभियन्ता, प्रथम वृत्त, लो0नि0वि0, अल्मोड़ा के पत्रांक 3477/383सी0-01/23, दिनांक 11.08.2023 द्वारा समरेखण प्रस्ताव स्वीकृत। -- as on 23-Aug-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: