Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.45 | 4.45 | 0.000 | 4.45 | 0.000 | 0.000 |
5W930 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/29112/2023 ई फाईल संख्या-47983, दिनांक 09.06.2023
TS Amount (lakhs) : 85.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
85.89
Resanction Cost :
85.89
Tentative Cost :
85.89
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 85.79
Demand : 50.00
Allotment : 40.00
Exp in CFY : 38.25
Total Up to Date Exp : 38.35
Construction Started
Physical Progress:
At start of FY 2024-2025 : 32 %
Up to Date : 32 %
Sanction on :
1 year 1 month ago
09 Jun 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2 किमी0 पहाड़ कटान कार्य पूर्ण शेष कार्य प्रगति पर। -- as on 01-Apr-2024
Physical Peramenters