Work Profile Report [5W937]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0-।/135768/2023, ई फाईल संख्या-35078, दिनांक 07.07.2023
TS Amount (lakhs) : 55.39 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
55.39
Resanction Cost :
55.39
Tentative Cost :
55.39
Exp. Upto Last Fy :
9.98
For CFY 2024-2025
Remaining :
45.41
Demand :
38.00
Allotment :
10.00
Exp in CFY :
0.00
Total Up to Date Exp :
9.98
Construction Started
Sanction on : 1 year 1 month ago
07 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
80 %
Tentative Completion date on : 1 month 6 days ago
10 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 25-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: