Work Profile Report : 5W938
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0-।/135768/2023, ई फाईल संख्या-35078, दिनांक 07.07.2023
TS Amount (lakhs) : 66.16 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
66.16
Resanction Cost :
66.16
Tentative Cost :
49.71
Saving
16.45
Exp. Upto Last Fy :
8.71
For CFY 2025-2026
Remaining :
57.45
Demand :
41.00
Allotment :
34.42
Exp in CFY :
34.42
Total Up to Date Exp :
43.13
Work completed
Sanction on : 2 years 6 months ago
07 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 7 hours ago
09 Jan 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 01-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: