Work Profile Report [5W980]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/42543/2023 (ई पत्रावली संख्या-48456) दिनांक 31.07.2023
TS Amount (lakhs) : 27.61 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
27.61
Resanction Cost :
27.61
Tentative Cost :
27.61
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
27.61
Demand :
20.00
Allotment :
20.00
Exp in CFY :
22.57
Total Up to Date Exp :
22.57
Work completed
Sanction on : 1 year 3 months ago
31 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
100 %
Tentative Completion date on : 8 months 1 week ago
15 Mar 2024
Actual Completion Date : 8 months 1 week ago
15 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 07-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: