Work Profile Report [5W987]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/144452/2023 ई फाईल संख्या-46395 दिनांक 07.08.2023
TS Amount (lakhs) : 223.3 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
223.30
Resanction Cost :
223.30
Tentative Cost :
200.30
Saving
23.00
Exp. Upto Last Fy :
47.90
For CFY 2024-2025
Remaining :
175.40
Demand :
141.68
Allotment :
60.00
Exp in CFY :
28.61
Total Up to Date Exp :
76.51
Construction Started
Sanction on : 1 year 4 months ago
07 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
40 %
Tentative Completion date on : 2 months 1 week from now
07 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी01 का कार्य पूर्ण, 1.50किमी0 जी02 , 0.80 किमी0 जी03 का कार्य पूर्ण। कल्वर्ट, रिटेनिंग वाल, ब्रेस्टवाल इत्यादि कार्य प्रगति पर। -- as on 03-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: Bhitarkot road Bridge