Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.675 | 2.675 | 0.000 | 2.675 | 1.670 | 0.000 |
5W995 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/164719/2023, फाईल संख्या-57670, दिनांक 27.10.2023
TS Amount (lakhs) : 230.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
230.61
Resanction Cost :
230.61
Tentative Cost :
230.61
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 230.61
Demand : 50.00
Allotment : 35.00
Exp in CFY : 11.25
Total Up to Date Exp : 11.25
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
8 months 2 weeks ago
27 Oct 2023
Tentative Completion date:
9 months 2 weeks from now
06 May 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार निर्माण, कच्ची एवं पक्की नाली निर्माण कार्य पूर्ण। काजवे की मरम्मत एवं पैरापिट निर्माण् कार्य प्रगति पर। -- as on 25-Jun-2024
Physical Peramenters