Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 21 | 21 | 21.000 | 0 | 0.000 | 0.000 |
No of Bridges | 2 | 0 | 0 | 0 | 0 | 0 |
Span of Bridges [m] | 80 | 0 | 0.000 | 0 | 0.000 | 0.000 |
Jobs | 1 | 0 | 0 | 0 | 0 | 0 |
60W2 :
Administrative Approval Detail : NH-28014/01/2014/UR/CRF/NH-2(Zone-1) dated 06-03-2019 (Job No. CRF-UR-2021-22-29 to 36) Uttarakhand Govt. Go 1311/III(3)/2020-28(CRF)/19 dt. 23.10.2020
TS Amount (lakhs) : 3332.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3332.41
Resanction Cost :
3332.41
Tentative Cost :
3332.41
Exp. Upto Last Fy : 2,513.01
For CFY 2024-2025
Remaining : 819.40
Demand : 0.00
Allotment : 20.00
Exp in CFY : 47.45
Total Up to Date Exp : 2,560.45
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
06 Mar 2019
Tentative Completion date:
1 year 11 months ago
31 Jul 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work Completed. -- as on 14-Dec-2023
Physical Peramenters