Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 0 | 0 |
61W12 :
Administrative Approval Detail : भारत सरकार के पत्र संख्या RO/UK/12014/93/Annual Plan/2019-20, Dt. 27-01-2020जाॅब संख्या NH-121 (309)-UR-2019-20-553
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
999.58
Resanction Cost :
999.58
Tentative Cost :
999.58
Exp. Upto Last Fy : 40.03
For CFY 2024-2025
Remaining : 959.55
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 40.03
Construction Started
Physical Progress:
At start of FY 2024-2025 : 14 %
Up to Date : 14 %
Sanction on :
4 years 5 months ago
27 Jan 2020
Tentative Completion date:
2 years 3 weeks ago
20 Jun 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
Diversion work completed. Well foundation work stopped by JIM Corbett Authority from Feb 2021 to 12-06-2021. After approval of CWLW, A2 well foundation work in progress.. -- as on 17-Aug-2021
Physical Peramenters