Work Profile Report [61W12]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : भारत सरकार के पत्र संख्या RO/UK/12014/93/Annual Plan/2019-20, Dt. 27-01-2020जाॅब संख्या NH-121 (309)-UR-2019-20-553
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
999.58
Resanction Cost :
999.58
Tentative Cost :
999.58
Exp. Upto Last Fy :
40.03
For CFY 2025-2026
Remaining :
959.55
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
40.03
Construction Started
Sanction on : 5 years 2 months ago
27 Jan 2020
Physical Progress:
At start of FY 2025-2026 :
14 %
Up to Date :
14 %
Tentative Completion date on : 2 years 9 months ago
20 Jun 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Diversion work completed. Well foundation work stopped by JIM Corbett Authority from Feb 2021 to 12-06-2021. After approval of CWLW, A2 well foundation work in progress.. -- as on 17-Aug-2021
Assets :