Work Profile

राष्ट्रीय राजमार्ग संख्या -121 (नया 309) के कि0मी0 1, 2, 3 में सुदृढ़ीकरण का कार्य।


Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

Administrative Approval Detail : भारत सरकार के पत्र संख्या RO/UK/Annual Plan/2020-21/Haldwani/06, Dt. 05-03-2021जाॅब संख्या NH-121 (309)-UR-2020-21-587

TS Amount (lakhs) : 351.99 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

351.99

Resanction Cost :

351.99

Tentative Cost :

351.99

Exp. Upto Last Fy : 0.00

For CFY 2024-2025

Remaining : 351.99

Demand : 0.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 0.00

Construction Started

Physical Progress:

At start of FY 2024-2025 : 4 %

Up to Date : 4 %

Sanction on :
3 years 4 months ago
05 Mar 2021


Tentative Completion date:
2 years 6 months ago
20 Dec 2021


Actual Completion Date:
Not Yet Reported


Rating : 4

Remark

Bottelneck:


Construction of Jersey Barrier work in progress. -- as on 16-Aug-2021

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 3.43 0 0
Currently only Bank Gaurantee information is avilable