Work Profile Report [61W21]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/ANNUAL PLAN/2022-23/HALDWANI-02(COMPUTER NO. 213703)
TS Amount (lakhs) : 4826 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4826.00
Resanction Cost :
4826.00
Tentative Cost :
4826.00
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
4,826.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 2 years 7 months ago
25 Oct 2022
Physical Progress:
At start of FY 2025-2026 :
89 %
Up to Date :
89 %
Tentative Completion date on : 1 month 4 weeks ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 4777.74 has been counted as tentative cost increased from 48.26 to 4826 . -- as on 01-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand