Work Profile Report [61W21]

राष्ट्रीय मार्ग संख्या 87 विस्तार (नया 109) के कि0मी0 0.00 से कि0मी0 45.00 तक आई0आर0क्यू0पी0 कार्य ।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : RO/UK/ANNUAL PLAN/2022-23/HALDWANI-02(COMPUTER NO. 213703)

TS Amount (lakhs) : 4826 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

4826.00

Resanction Cost :

4826.00

Tentative Cost :

4826.00

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

4,826.00

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Construction Started

Sanction on : 2 years 7 months ago

25 Oct 2022

Physical Progress:

At start of FY 2025-2026 :

89 %

Up to Date :

89 %

Tentative Completion date on : 1 month 4 weeks ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
45
45
45
-

Remark

view all

Overall Excess requirement 4777.74 has been counted as tentative cost increased from 48.26 to 4826 . -- as on 01-Mar-2025

Rating : 89

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand