Work Profile

एन0एच0 123(507) के किमी0 41.00 से 60.00 में रोड सुदढीकरण का कार्य।


Work not linked with IM

Roads on The Basis of AI: Road 1 Road 2

Bridges on The Basis of AI: Yamuna Bridge Badri bridge local nala

Administrative Approval Detail : RO/UK/12014/92/Annual plan/2019-20 dated 12.02.2020 ( job. no NH-123(507)-UR-2019-20-556)

TS Amount (lakhs) : 2314.03 Lacs

Financial Detail

Sanction Cost : 2,314.03 Lacs

Resanction Cost : 2,314.03 Lacs

Exp. Upto Last Fy : 1,458.98 Lacs

For CFY 2024-2025

Remaining : 855.05 Lacs

Demand : 0.00 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 1,458.98 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 100 %

Sanction on :
4 years 4 months ago
12 Feb 2020


Tentative Completion date:
2 years 4 months ago
20 Feb 2022


Actual Completion Date:
2 years 7 months ago
15 Nov 2021


Rating : 100

Remark

Bottelneck: no issue


physical progress-100.00%
DBM completed-19.00 km
BC completed- 19.00 km
-- as on 14-Jun-2022

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 19 19 19 0
Currently only Bank Gaurantee information is avilable