62W10 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UK/Annual Plan2022-23/Barkot/landslide (C.No. 219340) dated 20.02.2023
TS Amount (lakhs) : 5303.29 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5303.00
Resanction Cost :
5303.00
Tentative Cost :
5303.00
Exp. Upto Last Fy : 420.03
For CFY 2024-2025
Remaining : 4,882.97
Demand : 1,697.97
Allotment : 1,697.97
Exp in CFY : 1,697.96
Total Up to Date Exp : 2,118.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 51 %
Up to Date : 81 %
Sanction on :
1 year 4 months ago
20 Feb 2023
Tentative Completion date:
2 months 3 days from now
21 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
date of start -22.09.2023
physical progress- 81%
-- as on 14-Jul-2024