Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
Closed Work 63W4 :
Administrative Approval Detail : No. RO/UK12014/45/2018/Annual Plan Dated March 01,2019
TS Amount (lakhs) : 221.62 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
221.62
Resanction Cost :
221.62
Tentative Cost :
221.62
Exp. Upto Last Fy : 184.67
For CFY 2024-2025
Remaining : 36.95
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 184.67
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
01 Mar 2019
Tentative Completion date:
2 years 11 months ago
31 Jul 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck:
Work Completed -- as on 16-Aug-2021
Physical Peramenters