Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 20.146 | 20.146 | 20.146 | 0 |
Closed Work 63W9 :
Administrative Approval Detail : F.No. RO/UK/12014/111/Annual Plan /2019-20, Dated 07-01-2020
TS Amount (lakhs) : 1689.43 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1689.43
Resanction Cost :
1689.43
Tentative Cost :
1689.43
Exp. Upto Last Fy : 1,125.50
For CFY 2024-2025
Remaining : 563.93
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1,125.50
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
4 years 6 months ago
07 Jan 2020
Tentative Completion date:
2 years 2 days ago
15 Jul 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण हो चुका हो है। -- as on 08-Jan-2023
Physical Peramenters