Work Profile Report [67W229]

जनपद पौड़ी गढ़वाल में राज्य योजना के अन्तर्गत चमधार-सिरों-नउकोटी-खोगास-तीर-महड़-साकनीखेत मोटर मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0 7235/।।।घ्2घ्/11-139घ्प्रा0आ0घ्/2011 दिनांक 24-12-2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

126.00

Resanction Cost :

126.00

Tentative Cost :

126.00

Exp. Upto Last Fy :

113.96

For CFY 2025-2026

Remaining :

12.04

Demand :

2.32

Allotment :

2.32

Exp in CFY :

2.32

Total Up to Date Exp :

116.28

Phase1 DPR Submitted

Sanction on : 13 years 11 months ago

24 Dec 2011

Physical Progress:

At start of FY 2025-2026 :

50 %

Up to Date :

80 %

Tentative Completion date on : 8 months 2 weeks ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
0.000
10
0.000
0.000

Remark

view all

कास्तकारों से सम्पर्क कर मुआवजा वितरण की कार्यवाही गतिमान, (द्वितीय चरण का कार्य स्वीकृत वर्तमन में मार्ग यातायात के लिए सुलभ है। -- as on 23-Apr-2025

Rating : 90

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: