Work Profile Report [67W326]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0स0 5440/।।।(2)/14-26(प्रा0आ0)/2014 दि0 30.09.2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
13.90
Resanction Cost :
13.90
Tentative Cost :
13.90
Exp. Upto Last Fy :
3.15
For CFY 2024-2025
Remaining :
10.75
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3.15
Phase1 DPR Submitted
Sanction on : 10 years 2 months ago
30 Sep 2014
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
5 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
fद्वतीय चरण स्वीकृत। प्रfतकर भुगतान की कार्यवाही की जा रही है। -- as on 31-Jul-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand