Work Profile Report [67W462]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2843/।।।(2)/16-134(प्रा0आ0)/2011 दि0 20.10.2016
TS Amount (lakhs) : 397.09 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
397.09
Resanction Cost :
397.09
Tentative Cost :
397.09
Exp. Upto Last Fy :
369.56
For CFY 2024-2025
Remaining :
27.53
Demand :
27.00
Allotment :
20.00
Exp in CFY :
16.02
Total Up to Date Exp :
385.59
Work completed
Sanction on : 8 years 2 months ago
20 Oct 2016
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्य शेष। -- as on 06-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand