Work Profile Report [67W545]

नवन पल्ला से पथराडाखाल-गैठीछेडा मोटर मार्ग पर जोडने हेतु मोटर मार्ग का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : 635/।।।(2)/19-37(एम0एल0ए0)/2017टी0सी0 दि0 22.02.2019

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

43.92

Resanction Cost :

43.92

Tentative Cost :

43.92

Exp. Upto Last Fy :

10.27

For CFY 2024-2025

Remaining :

33.65

Demand :

2.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

10.27

Phase1 DPR Submitted

Sanction on : 5 years 5 months ago

22 Feb 2019

Physical Progress:

At start of FY 2024-2025 :

12 %

Up to Date :

12 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
2.25
2.25
0.000
2.25
0.000
0.000

Remark

view all

द्वितीय चरण स्वीकृत। प्रतिकर भुगतान की कार्यवाही की जा रही है। -- as on 04-Sep-2021

Rating : 29

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: