Work Profile Report [67W628]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1706/।।।(2)/21-37(एम0एल0ए0)2017टी0सी0-1 दि0 17.06.2021
TS Amount (lakhs) : 92.11 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
92.11
Resanction Cost :
92.11
Tentative Cost :
92.11
Exp. Upto Last Fy :
69.24
For CFY 2024-2025
Remaining :
22.87
Demand :
15.00
Allotment :
0.51
Exp in CFY :
0.51
Total Up to Date Exp :
69.76
Construction Started
Sanction on : 3 years 5 months ago
17 Jun 2021
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.50 कि0मी0 पहाड कटान का कार्य पूर्ण। -- as on 12-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand