Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.45 | 5.45 | 0.000 | 5.45 | 5.450 | 5.450 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W710 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 895/07याताा0-पी0एम0जी0एस0वाई0-नि0।।। दि0 16.05.2023
TS Amount (lakhs) : 88.48 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
88.48
Resanction Cost :
88.48
Tentative Cost :
88.48
Exp. Upto Last Fy : 19.68
For CFY 2024-2025
Remaining : 68.80
Demand : 68.80
Allotment : 19.13
Exp in CFY : 19.13
Total Up to Date Exp : 38.80
Work completed
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 2 weeks ago
27 Mar 2024
Actual Completion Date:
1 month 2 weeks ago
30 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। 1.50 कि0मी0 31.03.2024 तक पूर्ण कर लिया गया था। -- as on 27-Jun-2024
Physical Peramenters