Work Profile Report [67W710]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 895/07याताा0-पी0एम0जी0एस0वाई0-नि0।।। दि0 16.05.2023
TS Amount (lakhs) : 88.48 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
88.48
Resanction Cost :
88.48
Tentative Cost :
88.48
Exp. Upto Last Fy :
19.68
For CFY 2024-2025
Remaining :
68.80
Demand :
68.80
Allotment :
55.14
Exp in CFY :
55.14
Total Up to Date Exp :
74.82
Work completed
Sanction on : 1 year 7 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
100 %
Tentative Completion date on : 8 months 4 weeks ago
27 Mar 2024
Actual Completion Date : 6 months 3 weeks ago
30 May 2024
Physical Linear Components
Remark
कार्य पूर्ण। दायित्य शेष। -- as on 03-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: