Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 40 | 20.4 | 20.4 | 0 |
Closed Work 67W73 :
Administrative Approval Detail : शा0सं0 2491/111-2 /08-02घ्प्रा0आ0घ्/2008 दि0 25-07-2008
TS Amount (lakhs) : 1171.37 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1258.72
Resanction Cost :
1258.72
Tentative Cost :
1258.72
Exp. Upto Last Fy : 1,258.71
For CFY 2024-2025
Remaining : 0.01
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1,258.71
Work completed
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 0 %
Sanction on :
15 years 11 months ago
25 Jul 2008
Tentative Completion date:
11 years 8 months ago
31 Oct 2012
Actual Completion Date:
12 years 3 months ago
01 Apr 2012
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष।
Physical Peramenters